Cost Breakdown

Real Cost of Permits, Architect,
Engineer Combined

Oct 11, 2025 · 7 min read · By Dream Touch Renovations Ottawa

Real Cost of Permits, Architect, Engineer Combined
All articles

A Westboro client signed a renovation contract last spring. By the time the first wall came down, he'd spent a meaningful sum before the contractor hit a single nail. Permits, architectural drawings, structural engineer letter, surveyor for the property pin. That money was real. It came out of the same pocket as the renovation. He didn't budget for it.

The category is called soft costs. They are not optional, not negotiable below a floor, and they hit before construction starts. Below is what drives each piece for an Ottawa residential project, how they stack up by project type, and where homeowners get caught off guard. Every one of these lines appears, itemized, in the written proposal we give before a contract is signed.

The four soft-cost buckets

Every Ottawa renovation that touches structure, plumbing, electrical, or building footprint pulls money from these four buckets in roughly this order.

  1. Architectural or designer drawings: the package that gets submitted with the permit.
  2. Structural engineering: stamped letter or full structural drawings if walls are coming out.
  3. Building permit fees: paid to the City of Ottawa.
  4. Ancillary permits and reviews: ESA electrical, TSSA gas, Conservation Authority, heritage, minor variance, surveys.

Across all four buckets, soft costs typically land in the single-digit percentages of total project cost. The variance comes from project complexity, not contractor markup, and the bigger and more structural the project, the more these buckets fill.

Architectural and designer drawings

BCIN-certified designers and licensed architects produce the drawings the City needs to issue your permit. The Ontario Building Code allows BCIN designers (which is what we are) to do houses up to 9 metres tall and 600 square metres in area, which covers virtually all residential work.

Drawing scope, lowest effort to highest, roughly tracks this order in Ottawa:

Why the spread inside each category? Three things. First, complexity (number of trades, number of structural elements, number of code variances). Second, drawing depth (permit-only is the floor; full construction documents with details, schedules, and finishes is the ceiling). Third, who's drawing it: a BCIN designer bills at a lower hourly rate than a licensed architect, for the same legal authority on most residential work.

Structural engineering

Structural engineers (P.Eng.) are required when you remove load-bearing walls, build additions, alter foundations, or make changes the City flags during plan review. The stamped engineer letter is the document that says "yes, this beam will hold."

Engineering scope, lightest to heaviest:

The hidden engineering trigger

About 40 percent of "non-structural" Ottawa renovations end up needing an engineer once the walls open. The trigger is usually one of three things: the previous owner already removed a wall without a permit and we find a sistered joist instead of a beam; the existing beam is undersized for the new load; the addition's roof load needs to flow into existing rafters that weren't sized for it. Carry an engineering contingency on any project that touches walls so a surprise letter doesn't blow the budget.

City of Ottawa permit fees

Permits are calculated as a percentage of construction value, with a floor. The City publishes the schedule but the math in plain language:

Because the building permit is a percentage of construction value, permit cost rises with project scope. Smallest to largest:

The ancillary costs that surprise people

This is where the Westboro client's soft costs ate his budget. Most quotes don't list these because they vary by site:

The fastest way to blow up a renovation budget is to build the contract math without the soft costs. They are 4 to 9 percent of total project cost and they are all due before any wall comes down.

Bundled math by project type

What the soft costs tend to total, as a share of construction value, for common Ottawa projects. The percentage is the number to plan around, since it holds steadier than any dollar figure. Construction costs are separate.

Real example: Westboro 2025 (the client from the intro)

Rear addition (220 sq ft) plus full kitchen renovation. The soft-cost stack: drawings, a structural engineer for the addition, kitchen wall, and foundation tie-in, permits (building, plumbing, ESA, demolition), and a property survey. Together they came to roughly 7 percent of the construction contract, all due before the first wall came down. He had budgeted only the construction number and was over before construction started.

Where to save and where to overspend

Save here:

Spend here:

For our full permits and approvals process, including the BCIN-certified design + permit concierge service, see the Ottawa building permits page. The bottom line: budget 6 to 9 percent of construction value for soft costs, on top of construction. Anyone who tells you "permit's a couple hundred bucks" is selling you a quote you can't trust. Call 613-862-4555 for a fixed-price, all-in written proposal with every soft cost itemized.