A 1990s Nepean primary ensuite gut. New layout, tub under the window, double vanity, no-curb shower. Cost $68K. 7 weeks. Real numbers and choices.

May 10, 2026 · 6 min read · By Dream Touch Renovations Ottawa

← All articles

This primary ensuite bathroom renovation in a 1992 Nepean house off Greenbank took 7 weeks from demolition to the last bead of caulk. The 9 by 12 foot room was gutted and rebuilt with a freestanding tub under the window, a curbless 4 by 6 foot shower, a 72-inch floating double vanity and an electric heated floor.

Fixtures moved only along the existing wet wall, which kept the work out of the basement concrete below, and the curbless shower needed every joist under it sistered with LVL.

The house and the brief

1992 build, off Greenbank in Nepean. Original primary ensuite, never touched. The footprint was generous at 9 by 12 feet but the layout was the kind of thing that gets stamped into a thousand homes and never questioned: corner jetted tub on a tile pedestal, dated single vanity, builder shower stall with mottled glass, toilet right next to the shower in the worst possible sightline.

The owners had two non-negotiables. They wanted a freestanding tub under the window. They wanted a no-curb shower. Everything else was open.

The build took 7 weeks from demo morning to last bit of caulk, and the owners had a fixed written proposal in hand before we lifted a tool. Here is exactly how it went.

The new layout

The plumbing wall ran along the back of the room and continued through the wall to the powder room on the other side. We could move fixtures along that wall but moving them away from it would have meant breaking concrete in the basement below, which the owners did not want to fund.

The new arrangement, walking in:

The tub under the window is the move that made the whole project worth it. The window is 4 feet wide, north-facing onto a stand of mature trees. The owner takes baths in winter with the lights off and watches the sky. That memory is the reason this room exists.

No-curb shower: what it actually takes

Every bathroom client wants no-curb showers now and most of them do not understand what they involve or what they require.

To do it properly, you need to drop the floor in the shower zone by about 1.5 to 2 inches relative to the surrounding floor, slope it to the drain at minimum 2 percent, waterproof the entire wet area with a sheet membrane, and install a linear drain with a cover that sits flush with the finished tile.

In a renovation on a wood-frame floor, dropping the floor means cutting joists or sistering them with a notch, which is structural work. In this house we had 2x10 joists at 16 inches on centre.

We could not safely notch them more than the existing top flange would allow, so we sistered each joist in the shower zone with a flush-cut LVL strip on each side, then installed a curbless shower pan on top.

That is a meaningful block of structural and waterproofing work that would not have existed if they had picked a 4-inch curb. It is the main cost driver behind a curbless shower.

Curb vs no-curb: when each makes sense

No-curb showers age in place beautifully and require careful structural and waterproofing work, so they carry a premium over a curbed shower. They are worth it on the main level for an aging-in-place client. On a second-floor en-suite, weigh the added scope. A 4-inch curb does not look bad and the savings are real.

The materials

The brief was "warm modern, calm, not cold." Cold bathrooms are easy to do by accident. Cold means too much white, too much polished chrome, and too little contrast.

Heated floor: yes, do it

Adding an electric heated floor mat under the porcelain, including the dedicated thermostat and the 20-amp circuit, is a small line item relative to the whole job. The owners had it on a programmable schedule that warms the floor by 6:30 AM and turns off at 10 AM.

This is the single best small upgrade you can make in an Ottawa winter bathroom. Every previous client we have done it for says the same thing: they cannot imagine a bathroom without it now.

Heated floors do not feel like luxury after the first month. They feel like the way bathrooms should always have been.

Where the budget goes, line by line

Owners get an itemized written proposal before demo, so they know exactly what is included. These are the scope lines on a primary-ensuite gut like this one, ordered roughly by how much each drives the budget.

The biggest swing factors on a bathroom budget are tile selection and the labour to set it, whether fixtures are relocated off the existing wet wall, the shower type (curbed vs curbless), and the finish level of the vanity and counter. We walk through each with the owner before the proposal is fixed.

The 7-week timeline, week by week

Owners often ask what 7 weeks of bathroom work actually looks like. Here it is:

Permits and Costs for a Nepean Ensuite

Nepean is part of the City of Ottawa, so a Nepean bathroom permit comes from the City's Building Code Services. The Nepean Client Service Centre at 101 Centrepointe Drive offers some of those services in person, Monday to Friday from 8:30 am to 4:30 pm. The City exempts replacing bathroom cabinets only while the plumbing fixtures stay where they are.

This ensuite moved fixtures along the wet wall and sistered the floor joists under the shower, and the schedule above shows a City inspection in week 2. The heated floor's dedicated circuit is electrical work, and ESA expects the required notifications of work to be filed for it.

For bathroom renovations in Nepean on this scale, HomeStars' Ottawa cost guide, read 2026-10-05, names the size of the room and how much plumbing moves as the two biggest drivers. Both applied here: a primary ensuite, with fixtures moved along the wet wall. The sistered joists, the heated floor on its own circuit, the in-house white oak vanity and the Caesarstone counter added to it.

Who this kind of project suits

Nepean, Barrhaven, Kanata, Orleans, and Findlay Creek are full of 1985 to 2000 homes with the same dated primary ensuite. The footprint is usually fine. The layout was always wrong. A full ensuite gut, done properly, is the single highest-impact renovation you can do in those houses for resale and for daily life.

We have done over 200 of these now. The math is consistent: ensuites that were unusable beyond function become the room everyone uses first in the morning and last at night.

What the owners would do differently

One regret, six months in. They picked a single brushed-nickel finish across the room and now wish they had introduced a darker accent on the privacy wall hardware (towel hook, robe hook). The single-finish choice reads slightly bland on a dark winter morning. We are swapping those two pieces this spring for a minor hardware cost.

One thing they would do again without hesitation: the heated floor on a programmable thermostat. They originally hesitated over the added line item. They now describe it as the cheapest luxury they have ever bought.

The curbless shower and heated floor in this ensuite were planned for this room, not picked from a catalogue. Our bathroom renovation in Ottawa page sets out the Essential, Mid-Range and Premium scopes, and the Schluter-Kerdi membrane that goes under every shower we build.

If your ensuite needs the same treatment, see our bathroom renovation service or call 613-862-4555 for a free in-home walkthrough and a fixed-price quote. We also handle other renovations in Nepean, from kitchens to finished basements.

Frequently asked questions

What does a curbless shower require in a renovation?

A curbless shower requires dropping the floor in the shower zone about 1.5 to 2 inches below the surrounding floor, sloping it to the drain at a minimum of 2 percent, waterproofing the whole wet area with a sheet membrane, and installing a linear drain with a cover flush with the tile.

On a wood-frame floor that is structural work. In a Nepean ensuite with 2x10 joists at 16 inches on centre, each joist in the shower zone was sistered with a flush-cut LVL strip.

Should I choose a curbless shower or a curbed shower?

A curbless shower suits a main-level bathroom for an aging-in-place homeowner, where it ages beautifully and justifies the careful structural and waterproofing work behind it. On a second-floor ensuite, weigh that added scope first. A 4-inch curb does not look bad, avoids the joist work entirely, and the savings are real.

The main cost driver of a curbless shower is the structural floor drop and waterproofing that a curbed shower does not need.

Is a heated bathroom floor worth it in Ottawa?

A heated bathroom floor is the single best small upgrade for an Ottawa winter bathroom. An electric mat under porcelain needs a dedicated thermostat and a 20-amp circuit, and it is a small line item relative to a full renovation. A programmable schedule works well: one Nepean ensuite warms the floor by 6:30 AM and shuts off at 10 AM.

After the first month, a heated floor stops feeling like a luxury and starts feeling like the way bathrooms should be.

How long does a primary ensuite gut renovation take?

A primary ensuite gut renovation takes about 7 weeks from demo to final caulk. Week 1 covers demo and structural floor work, week 2 rough plumbing, electrical, framing and City inspection, and week 3 insulation and drywall.

Week 4 brings the waterproofing and heated floor mat, week 5 is a full week of tile, week 6 grout, vanity, counter and finishes, and week 7 the glass, touch-ups, final inspection and walkthrough.

How do you keep a new bathroom from feeling cold?

A bathroom feels cold when it has too much white, too much polished chrome and too little contrast. Warm it with warm-toned materials: a Nepean ensuite used honed travertine-look porcelain in warm beige, cream veined shower walls, white oak vanity fronts and a warm bone counter.

A single brushed-nickel finish kept that room calm, though the owners later wished for a darker accent on the towel and robe hooks, since one finish read slightly bland on dark winter mornings.

Official references

Want this kind of insight applied to your project?

Free in-home consultation. Fixed-price quote. An honest conversation about what's possible for your Ottawa home.

Get a Free Quote →

Dream Touch Renovations · 33 Roydon Pl, Suite 210, Ottawa, ON K2E 1A3 · (613) 862-4555

Renovating homes across Ottawa, Kanata, Nepean, Barrhaven, Orléans and Stittsville.

Free Quote →