Ottawa contractor's guide to renovation timing schedules around school: spring start vs summer vs fall, OCDSB calendar windows, and what trades book first.

Nov 28, 2025 · 6 min read · By Dream Touch Renovations Ottawa

← All articles

Every August, I get the same call. A family in Barrhaven or Riverside South wants their kitchen done before the kids start school. They want it started "as soon as possible" and finished by Labour Day. It's already August 12th. Permit hasn't been pulled. Cabinets are eight weeks out.

If you have school-age kids, the renovation timing schedule isn't just a preference. It's the difference between a project that runs smoothly and a project where you're feeding three kids cereal off a cardboard box on the laundry room floor in October. Here's how to plan it.

The four windows that matter for Ottawa families

Map your project against the OCDSB and OCSB calendar. Both follow roughly the same dates each year. The four windows worth planning around:

  1. Summer (late June to late August). 9 weeks. Best for kitchen and bathroom projects you want done before school starts.
  2. Winter break (mid-December to early January). 2 weeks. Useful only for small projects or as a buffer.
  3. March break (mid-March). 1 week. Too short for anything meaningful.
  4. The non-school months for full disruption (May-August). 4 months. The realistic window for full home or main floor renovations where the family stays in.

For projects bigger than a single room, the question isn't which window. It's which window you start in, knowing the project will run through several windows before it ends.

Match the project type to the window

Twenty years of running Ottawa renos has taught me which projects fit which windows. The honest version:

Kitchen renovation: 8-12 weeks

A kitchen reno run by a real crew with custom cabinets is 8-10 weeks if everything goes right, 12 if it doesn't. If you want it done before school starts, you start in early-to-mid June. Starting in July is too late unless you're using stock cabinets with a 2-week lead time.

The trap: cabinet lead times in Ottawa are 8-14 weeks for custom (we run our own shop, so we're at the short end), 6-10 weeks for semi-custom from companies like Cuisines Laurier or Cabico, and 2-4 weeks for IKEA. If you order in May, you can start demolition in late June and finish by mid-August. If you order in late June, your cabinets arrive in mid-September.

Bathroom renovation: 3-5 weeks

A single bathroom in 4 weeks is realistic. Two bathrooms back-to-back is 7-8 weeks. This is the rare project that fits cleanly into a summer window if you start by mid-July.

March break and winter break are too short for a full bathroom. You can sometimes squeeze a vanity-and-paint refresh into March break if the plumbing rough-in stays put.

Basement finish: 10-14 weeks

Basement renos run alongside life upstairs reasonably well. Dust gets contained on one floor; you don't lose your kitchen. Most families just live around it. Start anytime; finish whenever.

The exception: if the basement work involves the main electrical panel or HVAC ductwork, there will be 1-3 days of no-power and no-heat. Schedule that for warm weather.

Full main floor: 16-22 weeks

If you're renovating the kitchen, dining, living, and a powder room all at once, you're looking at 4-5 months minimum. There's no school window that fits this. Either you move out, or the family lives through the whole school year with the work happening around them.

For a deeper look at how full-home projects sequence, see our whole home renovation page.

Addition or second-storey: 5-8 months

You don't time these around school. You time them around weather. Excavation needs unfrozen ground (April-November), framing and roofing need workable conditions (May-October ideal), and you need the building closed in before December.

The realistic summer-only project sequence

For families who want a meaningful renovation done over summer break and the family in the home the whole time, here's what actually fits:

The September buffer trap

"We'll finish by Labour Day" turns into "we'll finish by Thanksgiving" more often than any single timeline I quote. Build a 3-week buffer past your target date before you commit to a back-to-school start. If your kid genuinely needs the house functional September 3rd, the project must finish August 10th on the contractor's schedule, not yours.

What to do during March break

One week is too short for almost anything. But it's a good week for these:

March break is also when families travel, which makes it useful for projects that need the house empty: hardwood refinishing (the smell is brutal for 4-5 days), full-house painting, or any work generating heavy dust.

What contractors are actually doing each season

The hidden factor in renovation timing is the contractor's own calendar. Here's what's true for most established Ottawa renovation firms:

"For a summer 2027 kitchen, you should be having the design conversation in September 2026. Earlier, ideally."

Booking a year out sounds excessive. It isn't. Custom cabinets need 8-14 weeks. Permits need 4-8 weeks. Design and engineering need 3-6 weeks. Order materials with summer lead times need 6-10 weeks. Add it all up and a real summer kitchen project starts in February.

The honest answer when timing breaks down

What if you genuinely need the project done now and the timing doesn't work? A few realistic alternatives:

  1. Use stock or semi-custom cabinets. Cuts cabinet lead time from 12 weeks to 3-4 weeks.
  2. Pre-order all materials before you finalize design. Counters, tile, flooring. They sit in the garage; you save 2-3 weeks of back-end waiting.
  3. Move the family out for the back-to-school window. Rent something for 4 weeks. The reno keeps running; the kids start school in a calm space; you move back in October.
  4. Split the project. Do the kitchen this summer; do the basement next summer. Most families overshoot what they can stomach in one season.

The biggest mistake families make is starting a renovation that's too big for the window they have. Half-finished kitchens at Christmas are real, and they're miserable. Sequence the work to fit, even if it means waiting another year for the rest.

Dream Touch builds renovation timelines the same way we build the projects: with realistic dates, real lead times, and a fixed-price quote that doesn't shift halfway through. Call 613-862-4555 for a free 48-hour feasibility review.

Frequently asked questions

When should a kitchen renovation start to finish before school starts?

A kitchen renovation meant to finish before school needs to start in early to mid June. A kitchen with custom cabinets takes 8 to 10 weeks if everything goes right and 12 if it does not, so a July start is too late unless stock cabinets with a 2-week lead time are used.

Order cabinets in May to start demolition in late June and finish by mid-August. A full kitchen with no layout change should start by June 20.

Can a bathroom renovation be done over summer break?

A single bathroom renovation fits into summer break. It takes 4 to 5 weeks and fits a June 25 to August 15 window with margin, as long as work starts by mid-July. Two bathrooms back to back take 7 to 8 weeks.

March break and winter break are too short for a full bathroom, though a vanity and paint refresh can sometimes fit into March break if the plumbing rough-in stays where it is.

What renovation projects fit into March break?

March break is one week, which suits only small projects. Painting a single room or hallway, installing or refinishing flooring in one room, replacing a powder room vanity, mirror and lighting, and swapping doors and trim across a floor all fit.

Most LVP installs take 2 to 3 days. Families often travel over March break, which also makes that week useful for work that needs an empty house, such as hardwood refinishing, full-house painting or heavy-dust jobs.

How far ahead should I book a summer kitchen renovation?

A summer kitchen renovation should be planned about a year ahead, with the design conversation in September for the following summer. Custom cabinets need 8 to 14 weeks, permits 4 to 8 weeks, design and engineering 3 to 6 weeks, and materials 6 to 10 weeks.

Added together, a real summer kitchen project starts in February. Most established Ottawa contractors are fully booked for June to September by late winter, so a May call for a summer start usually gets a no.

How much buffer should a renovation have before a back-to-school deadline?

A renovation should have a 3-week buffer past the target date before anyone commits to a back-to-school finish. A Labour Day finish often turns into a Thanksgiving finish. If a child needs the house functional on September 3rd, the project must be scheduled to finish on August 10th on the contractor's schedule.

When the timing breaks down, stock cabinets, pre-ordered materials, a short rental, or splitting the work across two summers are the realistic alternatives.

Official references

Want this kind of insight applied to your project?

Free in-home consultation. Fixed-price quote. An honest conversation about what's possible for your Ottawa home.